Georgia's Plant Vogtle achieves full power output from third nuclear reactor.

1 min read
Source: WSB Atlanta
TL;DR Summary

Unit 3 at Plant Vogtle in Georgia has reached its full output of 1,100 megawatts of electricity, enough to power an estimated 500,000 homes and businesses. The reactor is scheduled to enter commercial operation within the next month. The fourth reactor has finished a key testing phase and is expected to reach commercial operation between December and March 2024. Georgia Power owns 45.7% of the reactors, and almost every electric customer in Georgia will pay for Vogtle. The cost of the third and fourth reactors is now on track to cost the owners $31 billion.

Share this article

Reading Insights

Total Reads

0

Unique Readers

1

Time Saved

2 min

vs 3 min read

Condensed

82%

53695 words

Want the full story? Read the original article